Portfolio
Capital delivery — 6 projects in this browser workspace.
Projects by status
2 G / 3 Y / 1 R
Activities past due
2
Critical path this week
1
Missing controlling version
3
| Code | Project | RAG | Phase | Next milestone | High risks | Schedule | Docs | |
|---|---|---|---|---|---|---|---|---|
| HARE | Greenfield 345/138 kV Substation Crosby County, TX · A. Ramirez | Yellow | Execution | Transformer arrival / set Oct 16, 2026 | 2 | Watch8 crit | 100% | |
| TONTO | 138 kV Bay Addition Lea County, NM · J. Chen | Green | Execution | Protection settings applied Oct 09, 2026 | 0 | On track0 crit | 38% | |
| WINDMILL | Wind Interconnect Facilities Curry County, NM · S. Okonkwo | Yellow | Planning | IFC package Jan 15, 2027 | 0 | Watch1 crit | 25% | |
| MAYA | 69 kV Line Rebuild Hale County, TX · R. Delgado | Red | Execution | Steel delivery Nov 06, 2026 | 2 | Watch6 crit | 50% | |
| RANGER | Capacitor Bank Addition Potter County, TX · M. Singh | Green | Commissioning | In-service / SCADA handover Sep 25, 2026 | 0 | On track0 crit | 38% | |
| WHIPTAIL | Ring-Bus Conversion Lubbock County, TX · K. Brennan | Yellow | Execution | Breaker B12/B13 set Oct 16, 2026 | 0 | Watch3 crit | 25% |