Local workspace. Files stay in this browser unless you export a backup.

HARE

YellowExecution

Greenfield 345/138 kV Substation · Crosby County, TX · SPS Transmission — Capital Delivery

PM
% complete
Start
Finish
Parsed 20 of 20 rows. Column “activity_name” mapped to name.
Activities
20
Open
18
Critical
8
Near-critical
8
At risk
4
Overdue
2
Should have started
0
Open ends
2

Top 15 items leadership should know

  1. 1.HARE-2100 Control building foundation · TF -4 · Sep 11, 2026
  2. 2.HARE-2200 Transformer foundation and oil containment · TF -6 · Sep 25, 2026
  3. 3.HARE-4100 Set and dress 345/138 kV transformer · TF -2 · Nov 13, 2026
  4. 4.HARE-4300 P&C panels and yard cable · TF 0 · Dec 11, 2026
  5. 5.HARE-3300 Steel erection – high bus and A-frames · TF 0 · Nov 20, 2026
  6. 6.HARE-1100 Site grading and drainage · TF 2 · Jun 12, 2026
  7. 7.HARE-3100 345 kV transformer delivery · TF 0 · Oct 16, 2026
  8. 8.HARE-5300 Cutover / in-service · TF 0 · Feb 05, 2027
  9. 9.HARE-5100 Energization hold point – bus work complete · TF 0 · Dec 18, 2026
  10. 10.HARE-3200 Steel structures fabrication · TF 5 · Sep 30, 2026
  11. 11.HARE-1420 Ground grid and conduit · TF 6 · Sep 18, 2026
  12. 12.HARE-3400 345 kV bus and switches · TF 2 · Dec 18, 2026
  13. 13.HARE-1500 Stormwater / SWPPP inspections · TF 20 · Mar 05, 2027
  14. 14.HARE-4200 Control building erection · TF 3 · Oct 30, 2026
  15. 15.HARE-5200 Relay testing and SCADA point-to-point · TF 3 · Jan 22, 2027

Critical / at-risk Gantt

HARE-2200
HARE-2100
HARE-4100
HARE-3100
HARE-3300
HARE-4300
HARE-5100
HARE-5300
HARE-1100
HARE-3400
HARE-4200
HARE-5200
HARE-2300
HARE-3200
HARE-1420
HARE-1410
Mar 23, 2026Feb 5, 2027
IDNameStartFinishRDTF%StatusFlags
HARE-2200Transformer foundation and oil containmentJul 06, 2026Sep 25, 202618-655In ProgressCritical≤14dAt risk
HARE-2100Control building foundationJun 15, 2026Sep 11, 202612-472In ProgressCriticalOverdueAt risk
HARE-4100Set and dress 345/138 kV transformerOct 19, 2026Nov 13, 202619-20Not StartedCriticalAt risk
HARE-3100345 kV transformer deliverySep 08, 2026Oct 16, 202622015In ProgressCritical
HARE-3300Steel erection – high bus and A-framesOct 05, 2026Nov 20, 20263400Not StartedCritical
HARE-4300P&C panels and yard cableOct 19, 2026Dec 11, 20264000Not StartedCritical
HARE-5100Energization hold point – bus work completeDec 14, 2026Dec 18, 2026500Not StartedCritical
HARE-5300Cutover / in-serviceJan 25, 2027Feb 05, 20271000Not StartedCritical
HARE-1100Site grading and drainageMar 23, 2026Jun 12, 20268288In ProgressNear-criticalOverdueAt risk
HARE-3400345 kV bus and switchesNov 02, 2026Dec 18, 20263420Not StartedNear-critical
HARE-4200Control building erectionSep 14, 2026Oct 30, 202628318In ProgressNear-critical
HARE-5200Relay testing and SCADA point-to-pointDec 21, 2026Jan 22, 20272230Not StartedNear-critical
HARE-2300Dead-end and A-frame foundationsJul 20, 2026Oct 02, 202622448In ProgressNear-critical
HARE-3200Steel structures fabricationApr 06, 2026Sep 30, 202612590In ProgressNear-critical≤14d
HARE-1420Ground grid and conduitJun 22, 2026Sep 18, 20268686In ProgressNear-critical≤14d
HARE-1410138 kV line dropsNov 16, 2026Dec 11, 20262080Not StartedNear-critical
HARE-6100ROW restorationFeb 08, 2027Mar 05, 202720150Not StartedOpen end
HARE-1500Stormwater / SWPPP inspectionsMar 23, 2026Mar 05, 20271402045In ProgressOpen end
HARE-1000NTP and site mobilizationMar 02, 2026Mar 20, 202600100Completed—
HARE-1200Access road and fenceMay 04, 2026Jul 02, 2026012100Completed—

Longest-path style list

Built from successor/predecessor links when present; otherwise ranked by float, remaining duration, and near-term finish.

  1. HARE-1100 Site grading and drainage
  2. HARE-2300 Dead-end and A-frame foundations
  3. HARE-3200 Steel structures fabrication
  4. HARE-3300 Steel erection – high bus and A-frames
  5. HARE-3400 345 kV bus and switches
  6. HARE-5100 Energization hold point – bus work complete
  7. HARE-5200 Relay testing and SCADA point-to-point
  8. HARE-5300 Cutover / in-service
  9. HARE-6100 ROW restoration