HARE
YellowExecutionGreenfield 345/138 kV Substation · Crosby County, TX · SPS Transmission — Capital Delivery
- PM
- % complete
- Start
- Finish
Executive brief
HARE executive brief — demo seed (replace with Refresh AI brief)
• Greenfield 345/138 kV yard, all-steel, Wildfire Tier 2. PSOW Rev 2 is controlling.
• AM-003 increased transformer containment and added civil duration; no MVA change.
• Critical path sits on foundations: HARE-2200 TF -6, HARE-2100 TF -4 (snapshot 17-Sep-2026).
• Transformer delivery HARE-3100 is constrained Must Start 08-Sep; set HARE-4100 is successor.
• Steel erection HARE-3300 is not started (34d remaining, TF 0) behind fab and foundations.
• Energization hold point HARE-5100 is in the schedule; COM document is still Draft.
• SWPPP permit is controlling; weekly inspections called in ENV file.
• Cost forecast file is present but not controlling and does not support quoting dollars.
• Next milestone: transformer arrival / set, 16-Oct-2026 (project record).
• Recommended ask: recovery on HARE-2200 this week, and a signed commissioning procedure.
• Do not treat this demo brief as a live Grok analysis — use Refresh AI brief on current files.
Missing documents
Checklist categories are present.
No controlling version: Cost control, Commissioning
Open documentsOpen high risks
- Transformer foundation negative floatSchedule HARE-2200
- Transformer delivery on a must-start constraintSchedule HARE-3100 / AM-003
Critical path snapshot
Full scheduleData Date 17-Sep-2026 · 8 critical · 4 at risk · Watch
| ID | Name | Finish | TF |
|---|---|---|---|
| HARE-2100 | Control building foundation | Sep 11, 2026 | -4 |
| HARE-2200 | Transformer foundation and oil containment | Sep 25, 2026 | -6 |
| HARE-3100 | 345 kV transformer delivery | Oct 16, 2026 | 0 |
| HARE-3300 | Steel erection – high bus and A-frames | Nov 20, 2026 | 0 |
| HARE-4100 | Set and dress 345/138 kV transformer | Nov 13, 2026 | -2 |
| HARE-4300 | P&C panels and yard cable | Dec 11, 2026 | 0 |
| HARE-5100 | Energization hold point – bus work complete | Dec 18, 2026 | 0 |
| HARE-5300 | Cutover / in-service | Feb 05, 2027 | 0 |
Scope (PSOW + AMs)
HARE Greenfield 345/138 kV Substation — Project Scope of Work (Rev 2) Owner: SPS Transmission. Owner's Engineer: Capital Delivery OE desk. In scope: new 345/138 kV yard, one 345/138 kV transformer, control building, P&C, site civil, stormwater, fencing, and in-service support. Out of scope: 345 kV line construction beyond the dead-end, distribution getaways, and third-party fiber. All-steel structures. Wildfire Tier 2 construction controls apply. Key dates: NTP 2-Mar-2026; target in-service 5-Feb-2027. Interface: TOC outage window for cutover is owned by Operations, not the constructor.
Amendment AM-003 — Transformer foundation and oil containment upsizing. Adds 14 calendar days to foundation package. Containment volume increased per environmental review. No change to transformer MVA. Cost impact: not stated in this working file.