Local workspace. Files stay in this browser unless you export a backup.

HARE

YellowExecution

Greenfield 345/138 kV Substation · Crosby County, TX · SPS Transmission — Capital Delivery

PM
% complete
Start
Finish

Executive brief

HARE executive brief — demo seed (replace with Refresh AI brief)
• Greenfield 345/138 kV yard, all-steel, Wildfire Tier 2. PSOW Rev 2 is controlling.

• AM-003 increased transformer containment and added civil duration; no MVA change.

• Critical path sits on foundations: HARE-2200 TF -6, HARE-2100 TF -4 (snapshot 17-Sep-2026).

• Transformer delivery HARE-3100 is constrained Must Start 08-Sep; set HARE-4100 is successor.

• Steel erection HARE-3300 is not started (34d remaining, TF 0) behind fab and foundations.

• Energization hold point HARE-5100 is in the schedule; COM document is still Draft.

• SWPPP permit is controlling; weekly inspections called in ENV file.

• Cost forecast file is present but not controlling and does not support quoting dollars.

• Next milestone: transformer arrival / set, 16-Oct-2026 (project record).

• Recommended ask: recovery on HARE-2200 this week, and a signed commissioning procedure.

• Do not treat this demo brief as a live Grok analysis — use Refresh AI brief on current files.

Missing documents

Checklist categories are present.

No controlling version: Cost control, Commissioning

Open documents

Open high risks

  • Transformer foundation negative float
    Schedule HARE-2200
  • Transformer delivery on a must-start constraint
    Schedule HARE-3100 / AM-003

Critical path snapshot

Full schedule

Data Date 17-Sep-2026 · 8 critical · 4 at risk · Watch

IDNameFinishTF
HARE-2100Control building foundationSep 11, 2026-4
HARE-2200Transformer foundation and oil containmentSep 25, 2026-6
HARE-3100345 kV transformer deliveryOct 16, 20260
HARE-3300Steel erection – high bus and A-framesNov 20, 20260
HARE-4100Set and dress 345/138 kV transformerNov 13, 2026-2
HARE-4300P&C panels and yard cableDec 11, 20260
HARE-5100Energization hold point – bus work completeDec 18, 20260
HARE-5300Cutover / in-serviceFeb 05, 20270

Scope (PSOW + AMs)

HARE-PSOW-Rev2.txt · controlling

HARE Greenfield 345/138 kV Substation — Project Scope of Work (Rev 2) Owner: SPS Transmission. Owner's Engineer: Capital Delivery OE desk. In scope: new 345/138 kV yard, one 345/138 kV transformer, control building, P&C, site civil, stormwater, fencing, and in-service support. Out of scope: 345 kV line construction beyond the dead-end, distribution getaways, and third-party fiber. All-steel structures. Wildfire Tier 2 construction controls apply. Key dates: NTP 2-Mar-2026; target in-service 5-Feb-2027. Interface: TOC outage window for cutover is owned by Operations, not the constructor.

HARE-AM-003-Transformer-Pad.txt · controlling

Amendment AM-003 — Transformer foundation and oil containment upsizing. Adds 14 calendar days to foundation package. Containment volume increased per environmental review. No change to transformer MVA. Cost impact: not stated in this working file.