HARE
YellowExecutionGreenfield 345/138 kV Substation · Crosby County, TX · SPS Transmission — Capital Delivery
- PM
- % complete
- Start
- Finish
Total project estimate
$16,065,000
Through HARE-3100
$11,540,000
Unpriced lines
0
Estimates are working dollars in this browser, not a contractual commitment. Design (30%, 60%, 90%, and IFC) is included in the project total and in each milestone cumulative. Schedule phases follow the latest snapshot (Data Date 17-Sep-2026). A milestone cumulative adds design to every priced activity that finishes on or before that date.
Design
Phase $1,300,000
| Stage | Cumulative | Estimate |
|---|---|---|
DESIGN-30 30% design Cumulative $485,000 | ||
DESIGN-60 60% design Cumulative $895,000 | ||
DESIGN-90 90% design Cumulative $1,160,000 | ||
DESIGN-IFC Issued for construction (IFC) Cumulative $1,300,000 |
1.1 Civil
Phase $1,595,000
| Activity | Finish | % | Estimate |
|---|---|---|---|
HARE-1000 NTP and site mobilization Mar 20, 2026 | |||
HARE-1100 Site grading and drainage Jun 12, 2026 | |||
HARE-1500 Stormwater / SWPPP inspections Mar 05, 2027 | |||
HARE-1200 Access road and fence Jul 02, 2026 |
1.2 Foundations
Phase $2,880,000
| Activity | Finish | % | Estimate |
|---|---|---|---|
HARE-2100 Control building foundation Sep 11, 2026 | |||
HARE-1420 Ground grid and conduit Sep 18, 2026 | |||
HARE-2200 Transformer foundation and oil containment Sep 25, 2026 | |||
HARE-2300 Dead-end and A-frame foundations Oct 02, 2026 |
1.3 Equipment
Phase $5,850,000
| Activity | Finish | % | Estimate |
|---|---|---|---|
HARE-3200 Steel structures fabrication Sep 30, 2026 | |||
HARE-3100 345 kV transformer delivery Oct 16, 2026 |
1.4 Erection
Phase $3,390,000
| Activity | Finish | % | Estimate |
|---|---|---|---|
HARE-4200 Control building erection Oct 30, 2026 | |||
HARE-3300 Steel erection – high bus and A-frames Nov 20, 2026 | |||
HARE-4100 Set and dress 345/138 kV transformer Nov 13, 2026 | |||
HARE-3400 345 kV bus and switches Dec 18, 2026 | |||
HARE-1410 138 kV line drops Dec 11, 2026 |
1.5 P&C
Phase $610,000
| Activity | Finish | % | Estimate |
|---|---|---|---|
HARE-4300 P&C panels and yard cable Dec 11, 2026 |
1.6 Commissioning
Phase $320,000
| Activity | Finish | % | Estimate |
|---|---|---|---|
HARE-5100 Energization hold point – bus work complete Dec 18, 2026 | |||
HARE-5200 Relay testing and SCADA point-to-point Jan 22, 2027 | |||
HARE-5300 Cutover / in-service Feb 05, 2027 |
1.7 Closeout
Phase $120,000
| Activity | Finish | % | Estimate |
|---|---|---|---|
HARE-6100 ROW restoration Mar 05, 2027 |
Major milestones
Total $16,065,000
| Milestone | Finish | Cumulative |
|---|---|---|
HARE-1000 NTP and site mobilization | Mar 20, 2026 | $1,480,000 |
HARE-3100 345 kV transformer delivery | Oct 16, 2026 | $11,540,000 |
HARE-5100 Energization hold point – bus work complete | Dec 18, 2026 | $15,585,000 |
HARE-5300 Cutover / in-service | Feb 05, 2027 | $15,860,000 |