HARE

YellowExecution

Greenfield 345/138 kV Substation · Crosby County, TX · SPS Transmission — Capital Delivery

PM
% complete
Start
Finish
Total project estimate
$16,065,000
Through HARE-3100
$11,540,000
Unpriced lines
0

Estimates are working dollars in this browser, not a contractual commitment. Design (30%, 60%, 90%, and IFC) is included in the project total and in each milestone cumulative. Schedule phases follow the latest snapshot (Data Date 17-Sep-2026). A milestone cumulative adds design to every priced activity that finishes on or before that date.

Design

Phase $1,300,000
StageEstimate
DESIGN-30
30% design
Cumulative $485,000
DESIGN-60
60% design
Cumulative $895,000
DESIGN-90
90% design
Cumulative $1,160,000
DESIGN-IFC
Issued for construction (IFC)
Cumulative $1,300,000

1.1 Civil

Phase $1,595,000
ActivityEstimate
HARE-1000
NTP and site mobilization
Mar 20, 2026
HARE-1100
Site grading and drainage
Jun 12, 2026
HARE-1500
Stormwater / SWPPP inspections
Mar 05, 2027
HARE-1200
Access road and fence
Jul 02, 2026

1.2 Foundations

Phase $2,880,000
ActivityEstimate
HARE-2100
Control building foundation
Sep 11, 2026
HARE-1420
Ground grid and conduit
Sep 18, 2026
HARE-2200
Transformer foundation and oil containment
Sep 25, 2026
HARE-2300
Dead-end and A-frame foundations
Oct 02, 2026

1.3 Equipment

Phase $5,850,000
ActivityEstimate
HARE-3200
Steel structures fabrication
Sep 30, 2026
HARE-3100
345 kV transformer delivery
Oct 16, 2026

1.4 Erection

Phase $3,390,000
ActivityEstimate
HARE-4200
Control building erection
Oct 30, 2026
HARE-3300
Steel erection – high bus and A-frames
Nov 20, 2026
HARE-4100
Set and dress 345/138 kV transformer
Nov 13, 2026
HARE-3400
345 kV bus and switches
Dec 18, 2026
HARE-1410
138 kV line drops
Dec 11, 2026

1.5 P&C

Phase $610,000
ActivityEstimate
HARE-4300
P&C panels and yard cable
Dec 11, 2026

1.6 Commissioning

Phase $320,000
ActivityEstimate
HARE-5100
Energization hold point – bus work complete
Dec 18, 2026
HARE-5200
Relay testing and SCADA point-to-point
Jan 22, 2027
HARE-5300
Cutover / in-service
Feb 05, 2027

1.7 Closeout

Phase $120,000
ActivityEstimate
HARE-6100
ROW restoration
Mar 05, 2027

Major milestones

Total $16,065,000
MilestoneFinishCumulative
HARE-1000
NTP and site mobilization
Mar 20, 2026$1,480,000
HARE-3100
345 kV transformer delivery
Oct 16, 2026$11,540,000
HARE-5100
Energization hold point – bus work complete
Dec 18, 2026$15,585,000
HARE-5300
Cutover / in-service
Feb 05, 2027$15,860,000