YellowExecution

Greenfield 345/138 kV Substation · Crosby County, TX · SPS Transmission — Capital Delivery

PM
% complete
Start
Finish

Actions register

ProjectSourceActionSeverityOwnerStatusUpdated
HARESchedule HARE-2200Request a recovery plan for transformer foundation (overtime / additional crew) before 25-Sep so HARE-3100 set is not waiting on civil.HighSep 17, 2026, 12:00 PM
HAREDocument gap COMPromote a signed commissioning procedure to controlling version ahead of HARE-5100.MediumSep 17, 2026, 12:00 PM

Ask Grok

Ask a question — a weekly status, a recovery note, a document gap, or anything else in the files. Context: HARE.

Drafts library

HARE weekly — transformer pad on the critical path (DD 17-Sep-2026)

Draft

Leadership · weekly status · Sep 17, 2026, 12:00 PM